Party wall agreement form: what a party wall agreement pdf actually contains, and a party wall agreement example and party wall award example read side by side

A party wall award arrives as a bundle: a few pages of recitals and conditions, then a schedule of works, then a schedule of condition with photographs that is usually longer than everything else put together. People sensibly want to read it before it takes effect, and the thing that makes that hard is not the language but not knowing which part does what. Here is the anatomy, in the order the pages normally come, with what to look for in each.

The recitals and the appointments

The first pages name the building owner, the adjoining owner and the property, recite the notice that was served and the date, and record how the surveyors were appointed: one agreed surveyor, or one each with a third selected between them. Check the names and the property description are right, and check the notice date matches what you actually served, because everything downstream hangs off it. An error here is easy to correct at this stage and awkward later.

The authorised works and the conditions

Next comes what the building owner may do, described tightly, followed by the conditions on doing it: hours of work, notice before access, protection of the neighbour's property, making good, and how any damage is dealt with. This is the operative part of the document and the part worth reading twice. If something you agreed verbally with the neighbour is not written here, it is not in the award, and a party wall agreement example from another job is no help on this section because the conditions are the bit that is genuinely particular.

The schedule of condition and the fees

The schedule of condition records the state of the adjoining owner's property before work, room by room and elevation by elevation, with photographs and dated notes. It is the single most valuable page in the bundle if a crack appears later. Last come the fees: who pays the surveyors, and how much. A party wall award example from a different job will show a different figure, which is why the cost worksheet on this site takes the rates you have actually been quoted rather than publishing an average.

Questions people ask about party wall agreement form

Do I have to sign the award?

No. An award is served on the parties, not signed by them; the surveyors make it. Either party may appeal to the county court within a short window after it is served, and otherwise it is conclusive and binds you both.

What if the schedule of condition has missed a room?

Say so before the work starts, in writing, to the surveyors. Once the work has begun, a room that was never recorded is an argument rather than a record, and the argument is one you are unlikely to win.

Can I get the award as a pdf?

Almost always. Ask for it, keep it with the notice and the proof of service, and keep the photographs at full size rather than compressed into the document, because the detail is the point of them.