Schedule of condition report

Items the schedule will hold
32
Photographs to take
64
Time on site, minutes
126
Rough length of the report, pages
17

Every answer on this site comes out of the figures you type and the method printed beside them: your start date, your adjoining owners, your rooms and elevations, your surveyor's hourly rate. Where a period comes from the Act rather than from you, the section is linked so you can read it. Statutory periods are counted at their longest, two calendar months as 62 days and one as 31, so a date this site gives you is never short of what the Act asks.

Your numbers

The figures above start from a worked example (32). Change any input and the answer updates as you type, the way it will on the address record.

Download the Schedule of condition report worked example (CSV)

The Abutly workspace on the notices, awards and schedules tab with the schedule of condition for 44 Ashgrove Terrace open: 8 rooms to record, 2 external elevations, 6 photographs and 3 existing defects per room, 12 minutes a room and 3 copies to serve, and against them 32 items the schedule will hold, 64 photographs to take, 126 minutes on site, 17 pages and 51 printed pages across every copy, with the reference SC-2026-118 saved on the record
Pro kept the schedule of condition sizing with the notices it belongs to, which is where it has to be when the neighbour asks about a crack years after the work.

This worksheet sizes a schedule of condition, the photographic record of the adjoining owner's property taken before the work starts. Enter the rooms and external elevations you will record, the photographs and existing defects per room and how long a room takes, and it gives you the items the schedule will hold, the photographs to take, the time on site in minutes, a rough length in pages and the printed pages across every copy you have to serve. A schedule that misses a room is worth very little later, so the point of counting first is to book enough time.

What a building owner asks before running the Schedule of condition report

Which rooms should go in? Every room on the adjoining owner's side that could plausibly be affected, plus the elevations facing the work. Surveyors differ on how far to go, but the room you leave out is the room the crack appears in, and adding one takes minutes on site and nothing at all afterwards.

Why does it count printed pages? Because the schedule is served, and every party gets a copy. A schedule that runs to seventeen pages becomes fifty-one across three copies, which is the difference between printing it in the office and sending it out.

Does a schedule of condition stop a dispute? No, but it decides one. Without it, an argument about whether a crack was there before the work is two memories against each other; with it, it is a dated photograph. That is why it is attached to almost every award.

Where the constants in this tool come from

Party Wall etc. Act 1996, section 10: resolution of disputes.

GOV.UK, Party walls and building work.

Party Wall etc. Act 1996, contents.

Start Abutly ProKeep the notices, not a folder of scans