Party wall notice template

Notices to serve in this job
4
Days left to serve a party structure notice
26
Days left to serve an adjacent excavation notice
57
Days left to serve a line of junction notice
57

Every answer on this site comes out of the figures you type and the method printed beside them: your start date, your adjoining owners, your rooms and elevations, your surveyor's hourly rate. Where a period comes from the Act rather than from you, the section is linked so you can read it. Statutory periods are counted at their longest, two calendar months as 62 days and one as 31, so a date this site gives you is never short of what the Act asks.

Your numbers

The figures above start from a worked example (4). Change any input and the answer updates as you type, the way it will on the address record.

Download the Party wall notice template worked example (CSV)

The Abutly workspace signed in as Priya Raghunathan, on the notices, awards and schedules tab, with three saved documents listed and the notice schedule for 42 Ashgrove Terrace open beneath its row: 90 days until the work starts, 2 adjoining owners to serve, 1 party structure notice and 1 adjacent excavation notice, 0 line of junction notices and 2 days allowed for post, and against them 4 notices to serve, 26 days left to serve the party structure notice, 57 days for the adjacent excavation notice and the line of junction notice, and a notice pack of 10 pages, with the reference NS-2026-118 saved on the record
Pro kept the notice schedule as it was counted: the start date and the owners that went in, the notices and the days left they produced, saved against the job with its reference and reopenable in the worksheet.

This worksheet counts the party wall notices a job needs and the days you have left to serve each one. Enter how far away your start date is, how many adjoining owners there are, and how many of each kind of notice the work calls for, and it gives you the total number of notices to write, the days left to serve a party structure notice, an adjacent excavation notice and a line of junction notice, and the rough length of the pack. Statutory periods are counted at their longest, two calendar months as 62 days and one month as 31, so the date it gives you is never short of what the Act asks.

What a building owner asks before running the Party wall notice template

Why does it count two months as 62 days? Because two calendar months is between 59 and 62 days depending on where in the year it falls, and a notice that is a day short is not a valid notice. Counting at the longest means the date this worksheet gives you works in July as well as in February.

Why is the answer per owner rather than per house? Because the Act serves owners, not buildings. A house next door with one freeholder is one adjoining owner; a converted house with a leaseholder above, a leaseholder below and a freeholder is three, and each of them gets their own notice of each kind.

What if the number of days left comes out negative? Then the start date is inside the notice period and something has to move: the start date, or the job. A negative answer here is the useful one, because it is far cheaper to find out now than after the builder has booked the scaffolding.

Where the constants in this tool come from

Party Wall etc. Act 1996, section 3: party structure notices.

Party Wall etc. Act 1996, section 1: new building on line of junction.

Party Wall etc. Act 1996, section 6: adjacent excavation and construction.

Start Abutly ProKeep the notices, not a folder of scans